As of April 2015
During our last meeting we approved a set of community projects. Here’s the project map:
and the list:
Is ROW? | Key | Task | Size/What | Resources | Duration |
✓ | W4 | CR ROW clearing | 0.6 acres (1700*15) | Swift Crew 10 man | 1 day |
W5 | Forest Service Fuel break | Briefs with N7, E14 & E12 | 2 people to brief the FS | 1 day | |
✓ | W6 | Half of Edwards Road ROW clearing | Frontage to absent land | Swift Crew 10 man | 1 day |
W7 | South Private Land Fuel break | Needs a route specified to calculate all fields | |||
✓ | N4 | Turner Road ROW clearing | 0.66 acres (1815*15) | Swift Crew 10 man | 0.50day |
N5 | County Easement walkway | .22 acres (30*300) | Swift Crew 20 man | 1 day | |
N6 | Gully up-slope Zone 2 thinning | 2.0 acres | Swift Crew 20 man | 3 days | |
N7 | Forest Service Fuel break | Briefs with W5, E14 & E12 | E14 is the E FS fuelbreak | ||
E12 is the escape route | |||||
✓ | E4 | The Gauntlet ROW | Complete the corner and drainage section | 0.5 day | |
E5 | Gully up-slope Zone 2 thinning | 4.0 acres; cut, drag and stack slash to burn | CUSP chipper & sawyer | 3 days | |
E6 | Boundary Thicket in county ROW | 100 sq. feet | crew, CWPP Vol. crew | 3 hours | |
✓ | E7 | Mt. Herman Ln ROW clearing | 0.5 acres | Swift Crew 10 man | 1 day |
E8 | E Gauntlet, thinning 2 drainages | 1000 sq feet | CWPP Volunteer crew | 1 day | |
E9 | W Gaunlet, thinning 1st drainage | 2.0 acres | Swift Crew 20 man | 0.5 days | |
✓ | E10 | Dolittle’s isolated gully ROW clearing | 1000 sq feet | CUSP chipper & sawyer crew, CWPP Vol. Crew | 0.5 days |
E11 | W Gauntlet, thinning 2nd Drainage | 2.0 acres | Swift Crew 10 man | 0.5 days | |
✓ | S4 | Evans Road ROW clearing | Swift Crew 10 man | 0.5 days | |
S5 | Fallon Road ROW clearing | 0.175 acres (300*24) | Swift Crew 10 man | 1 day | |
S6 | Private Land Drainage fuel break | 0.25 acres | Swift Crew 10 man | 1 day | |
E12 | Escape Route | Forest service land | 2 people to brief the FS | 1 day |
[…] The Projects […]